True/False
Indicate whether the sentence or statement is true
or false.
|
|
|
1.
|
You
can create unique calendars for tasks and resources that do not follow the working and nonworking
times specified by the Standard calendar.
|
|
|
2.
|
By
default, all tasks and resource assignments inherit the project calendar unless you specify something
else.
|
|
|
3.
|
Project 2003 does not allow in-cell editing.
|
|
|
4.
|
In
Project 2003, pressing the Delete key anywhere in a task row deletes the entire row for that
task.
|
|
|
5.
|
Milestones can be used to motivate project participants by recognizing
accomplishments.
|
|
|
6.
|
A
computer must be installed before application software can be installed; this relationship between
these two tasks is an example of a Finish-to-Start task dependency type.
|
|
|
7.
|
As
soon as you start installing hardware, you can start documenting serial numbers; the relationships
between these two tasks is an example of a Finish-to-Finish task dependency type.
|
|
|
8.
|
A
computer backup must be finished before the shutdown of the system is completed; this relationship
between these two tasks is an example of a Start-to-Start task dependency type.
|
|
|
9.
|
In
the event of a power interruption, the UPS must start before the operator can finish shutting down
the system in an orderly fashion; this relationship between the two tasks is an example of a
Finish-to-Start task dependency type.
|
|
|
10.
|
Creating task dependencies does not affect the start and finish dates of the linked
tasks.
|
|
|
11.
|
Changing and linking tasks affects the critical path.
|
|
|
12.
|
Sometimes a task is a predecessor to more than one task, and therefore the process of
dragging link lines in a graphical view becomes laborious.
|
|
|
13.
|
In a
Finish-to-Start relationship, a -25% lag time pulls the second task forward in time; the second task
will not start until after the first task is completed plus an additional 25% of the duration of the
first task.
|
|
|
14.
|
Lag
time can only be applied to the Finish-to-Start and Start-to-Finish dependency types.
|
|
|
15.
|
Projects can have at most one level in the WBS.
|
Multiple Choice
Identify the
letter of the choice that best completes the statement or answers the question.
|
|
|
16.
|
The
____ calendar is the base calendar used by Project 2003 to schedule new tasks within the
project. a. | task | b. | project | c. | main | d. | origin | | |
|
|
|
17.
|
Working days appear ____ on the Standard calendar. a. | as light
gray | b. | with gray
diagonal lines | c. | as red | d. | as
white | | |
|
|
|
18.
|
Nonworking days appear ____ on the Standard calendar. a. | as light
gray | b. | with gray
diagonal lines | c. | as red | d. | as
white | | |
|
|
|
19.
|
If a
day of the week such as Monday or Tuesday is edited on the calendar, the days abbreviation is
____. a. | bold | b. | italicized | c. | underlined | d. | in red | | |
|
|
|
20.
|
To
select noncontiguous days on the calendar, you would click the first day and then press and hold the
____ key while clicking the other days to select them as a group.
|
|
|
|
|
|
21.
|
The
item indicated in the figure above is the ____ indicator. a. | Gantt
Chart | b. | Calendar | c. | Network
Diagram | d. | None of the above | | |
|
|
|
22.
|
The
____ key moves the active cell right one cell.
|
|
|
23.
|
The
____ key moves the active cell to the last column in a row. a. | Page
Down | b. | F6 | c. | Ctrl | d. | End | | |
|
|
|
24.
|
The
____ keys move the active cell to the first column of the first row. a. | Ctrl +
Home | b. | Shift +
Home | c. | Alt +
Home | d. | Esc +
Home | | |
|
|
|
|
|
|
25.
|
The
item indicated in the figure above is a ____. a. | fill handle | b. | Constraint
marker | c. | Smart Tag | d. | Delete
flag | | |
|
|
|
26.
|
The
abbreviation for elapsed minute is ____.
|
|
|
|
|
|
27.
|
The
item indicated in the figure above is a(n) ____ duration. a. | elapsed | b. | postponed | c. | eliminated | d. | estimated | | |
|
|
|
28.
|
If a
given column displays a series of ____, the information is too wide to display within the width of
the column. a. | pound
signs | b. | question marks | c. | exclamation
points | d. | ampersands | | |
|
|
|
|
|
|
29.
|
Item
2 indicated in the figure above is the ____ indicator. a. | row | b. | Recurring task | c. | Collapse | d. | Summary task | | |
|
|
|
30.
|
A(n)
____ has a zero duration and is a symbolic task used mainly to communicate progress or to mark the
end of a significant phase of the project. a. | origin point | b. | destination | c. | milestone | d. | summation | | |
|
|
|
31.
|
By
far the most common task dependency is ____.
|
|
|
|
|
|
32.
|
The
item marked 1 in the figure above is a ____ task dependency. a. | Finish-to-Finish | b. | Start-to-Finish | c. | Finish-to-Start | d. | Start-to-Start | | |
|
|
|
33.
|
The
item marked 4 in the figure above is a ____ task dependency. a. | Finish-to-Finish | b. | Start-to-Finish | c. | Finish-to-Start | d. | Start-to-Start | | |
|
|
|
34.
|
In
the Network Diagram view, the critical tasks are displayed within a ____ border. a. | blue | b. | silver | c. | black | d. | red | | |
|
|
|
35.
|
Which
of the following views does not show link lines? a. | Gantt Chart | b. | Network
Diagram | c. | Calendar | d. | All of the
above | | |
|
|
|
|
|
|
36.
|
The
time marked 1 in the figure above is called ____ time. a. | negative lag
time | b. | lead
time | c. | lag
time | d. | Both A and
B | | |
|
|
|
37.
|
A(n)
____ is an outcome-oriented analysis of the work involved in a project that defines the total scope
of the project. a. | summary
task | b. | WBS | c. | ISL | d. | scope analysis | | |
|
|
|
38.
|
____
tasks are groups of tasks that logically belong together. a. | Aggregate | b. | Clustered | c. | Summary | d. | Grouped | | |
|
|
|
|
|
|
39.
|
The
item marked 1 in the figure above is a(n) ____ task. a. | aggregate | b. | clustered | c. | grouped | d. | summary | | |
|
|
|
40.
|
The
item marked 2 in the figure above is a(n) ____ task bar. a. | summary | b. | grouped | c. | clustered | d. | aggregate | | |
|